Once again working collaboratively with our business partner, RUC Mining and its team at Appin Mine Shaft Operations, we have helped them achieve some significant project milestones:
The sinking stage was expertly assembled and safely chaired in the shaft, with the lift weighing in at just under 70 tonnes (including proof load) – achieved with precise planning and preparation!
In collaboration with Eilbeck Heavy Machining, we manufactured and mobilised two Rucshaw 5/12 winders
A flawless first blast means the pre-sink is now complete down to a depth of 50 metres